KEY FIGURES |
Customer: |
Ford Avon Lake |
Project Value: |
$1,400,000 |
Project Type: |
Industrial |
Region: |
Midwest |
TRADES INVOLVED |
Paint Circulation System |
Upgrade to the paint system in Booth 2 for a new product. Conti installed 20,000 ft of 1-1/2" SS tubing supplying paint from the mix room to the paint booths. |
Installed 80% of tubing and equipment during production and without interrupting operations. Shut down and cleaned existing paint piping during a 10 day downtime to switch to the new system. |